N84 Grid

Giffordland 400/132kV

NESO connection site, host SPT.

Contracted here0.30 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date7 May 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue300 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Sand Quarry Old Glasgow Road BESS31 May 20247 May 2029100 MW
GIFFORDLAND 200MW FIELD BESS22 Jul 202530 Apr 2033200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2029: 100 MW2033: 300 MW20292030203120322033300 MW
0 MW200 MW400 MW2029: 100 MW2033: 300 MW202920312033300 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029100 MW
2033300 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Sand Quarry Old Glasgow Road BESS100 MW0 MW7 May 2029not statedgate not printedScoping
2GIFFORDLAND 200MW FIELD BESS200 MW100 MW30 Apr 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291100 MW
20331200 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
GIFFORDLAND 200MW FIELD BESSBattery storage200 MW30 Apr 2033Scoping
Sand Quarry Old Glasgow Road BESSBattery storage100 MW7 May 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.