The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Cloud Hill Windfarm
31 May 2024 to 31 May 2030 (gate not printed) - Cloud Hill Windfarm
31 May 2024 to 31 Oct 2036 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Cloud Hill Windfarm | 31 May 2024 | 31 May 2030 | 50 MW |
| Cloud Hill Windfarm | 31 May 2024 | 31 Oct 2036 | 10 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2030 | 50 MW |
| 2036 | 60 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Cloud Hill Windfarm | 50 MW | 0 MW | 31 May 2030 | not stated | gate not printed | Awaiting Consents |
| 2 | Cloud Hill Windfarm | 10 MW | 50 MW | 31 Oct 2036 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2030 | 1 | 50 MW |
| 2036 | 1 | 10 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Cloud Hill Windfarm | Hybrid | 60 MW | 31 Oct 2036 | Scoping |
| Twentyshilling Wind Farm | Onshore wind | 37.8 MW | not stated | Built |
| Whiteside Hill Wind Farm | Onshore wind | 27 MW | not stated | Built |
| Wardpark Bravo Generating Station | Gas | 4 MW | not stated | Built |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.