N84 Grid

Glenrothes GSP

NESO connection site, host SPT.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Jul 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue95.9 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Glenrothes BESS31 May 202430 Oct 202546 MW
Pitkevy Battery Storage7 Nov 202531 Jul 202449.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2024: 50 MW2025: 96 MW2024202596 MW
0 MW50 MW100 MW2024: 50 MW2025: 96 MW2024202596 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202449.9 MW
202595.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Glenrothes BESS46 MW0 MW30 Oct 20252gate 2Consents Approved
2Pitkevy Battery Storage49.9 MW46 MW31 Jul 2024not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024149.9 MW
2025146 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Markinch (Rothes) Biomass CHP PlantBiomass and waste55 MWnot statedBuilt
Roaring Hill Energy Storage FacilityBattery storage49.99 MWnot statedBuilt
Pitkevy Battery StorageHybrid49.9 MW31 Jul 2024Scoping
Glenrothes BESSBattery storage46 MW30 Oct 2025Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.