Greens 400kV Substation

NESO connection site, host SHET.

Contracted here3.50 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Mar 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,500 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Caledonia Offshore Wind Farm31 May 202431 Mar 2031600 MW
Caledonia Offshore Wind Farm31 May 202431 Oct 20321,400 MW
Stromar Offshore Windfarm31 May 202431 Oct 20331,000 MW
Stromar Offshore Windfarm31 May 202431 Dec 2035500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2031: 600 MW2032: 2.0 GW2033: 3.0 GW2035: 3.5 GW203120322033203420353.5 GW
0 MW2.0 GW4.0 GW2031: 600 MW2032: 2.0 GW2033: 3.0 GW2035: 3.5 GW2031203320353.5 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031600 MW
20322,000 MW
20333,000 MW
20353,500 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Caledonia Offshore Wind Farm600 MW0 MW31 Mar 2031not statedgate not printedScoping
2Caledonia Offshore Wind Farm1,400 MW600 MW31 Oct 2032not statedgate not printedScoping
3Stromar Offshore Windfarm1,000 MW2,000 MW31 Oct 2033not statedgate not printedScoping
4Stromar Offshore Windfarm500 MW3,000 MW31 Dec 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311600 MW
203211,400 MW
203311,000 MW
20351500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
North East Offshore Wind FarmOffshore wind2,000 MW31 Oct 2032Scoping
Cygnus Offshore WindfarmOffshore wind1,500 MW31 Dec 2035Scoping

Supported by National Energy SO Open Data