N84 Grid

Gremista GSP

NESO connection site, host SHET.

Contracted here0.19 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date7 Nov 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue185.8 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Zenobe Shetland BESS7 Nov 20257 Nov 202568 MW
Girlsta7 Nov 202530 Sep 202918 MW
Neshion Energy Park7 Nov 202531 Oct 203549.9 MW
Gremista Energy BESS7 Nov 202531 Oct 203549.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2025: 68 MW2029: 86 MW2035: 186 MW202520272029203120332035186 MW
0 MW100 MW200 MW2025: 68 MW2029: 86 MW2035: 186 MW2025202820312035186 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202568 MW
202986 MW
2035185.8 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Zenobe Shetland BESS68 MW0 MW7 Nov 2025not statedgate not printedScoping
2Girlsta18 MW68 MW30 Sep 2029not statedgate not printedScoping
3Neshion Energy Park49.9 MW86 MW31 Oct 20351gate 1Scoping
4Gremista Energy BESS49.9 MW135.9 MW31 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2025168 MW
2029118 MW
2035299.8 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Zenobe Shetland BESSBattery storage68 MW7 Nov 2025Scoping
Neshion Energy ParkHybrid49.9 MW31 Oct 2035Scoping
Gremista Energy BESSBattery storage49.9 MW31 Oct 2035Scoping
GirlstaHybrid18 MW30 Sep 2029Scoping
Lerwick HydrogenBattery storage0 MW31 May 2029Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.