The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Gammidge PV & BESS Park
31 May 2024 to 15 Oct 2027 (gate 1) - Grendon Solar & BESS
31 May 2024 to 1 Jul 2029 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Gammidge PV & BESS Park | 31 May 2024 | 15 Oct 2027 | 40.9 MW |
| Grendon Solar & BESS | 31 May 2024 | 1 Jul 2029 | 500 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 40.9 MW |
| 2029 | 540.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Gammidge PV & BESS Park | 40.9 MW | 0 MW | 15 Oct 2027 | 1 | gate 1 | Scoping |
| 2 | Grendon Solar & BESS | 500 MW | 40.9 MW | 1 Jul 2029 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 40.9 MW |
| 2029 | 1 | 500 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Grendon Solar & BESS | Hybrid | 500 MW | 1 Jul 2029 | Scoping |
| Gammidge PV & BESS Park | Battery storage | 40.9 MW | 15 Oct 2027 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.