The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Lochluichart Battery Storage
7 Nov 2025 to 30 May 2028 (gate 2) - Three Lochs Hydro
7 Nov 2025 to 30 Jun 2024, date already passed (gate not printed) - Achanalt Battery Storage
22 Jul 2025 to 31 Oct 2027 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Lochluichart Battery Storage | 7 Nov 2025 | 30 May 2028 | 49.9 MW |
| Three Lochs Hydro | 7 Nov 2025 | 30 Jun 2024 | 2 MW |
| Achanalt Battery Storage | 22 Jul 2025 | 31 Oct 2027 | 49.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 2 MW |
| 2027 | 51.9 MW |
| 2028 | 101.8 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Lochluichart Battery Storage | 49.9 MW | 0 MW | 30 May 2028 | 2 | gate 2 | Scoping |
| 2 | Three Lochs Hydro | 2 MW | 49.9 MW | 30 Jun 2024 | not stated | gate not printed | Consents Approved |
| 3 | Achanalt Battery Storage | 49.9 MW | 51.9 MW | 31 Oct 2027 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 2 MW |
| 2027 | 1 | 49.9 MW |
| 2028 | 1 | 49.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Lochluichart Battery Storage | Battery storage | 49.9 MW | 30 May 2028 | Scoping |
| Achanalt Battery Storage | Battery storage | 49.9 MW | 31 Oct 2027 | Scoping |
| Grudie Bridge (SSE GENERATION LIMITED) | Hydro and pumped storage | 18.7 MW | not stated | Built |
| Wyvis Hydro Generating Station | Hydro and pumped storage | 3.9 MW | not stated | Built |
| Attadale Hydro | Hydro and pumped storage | 3.5 MW | not stated | Built |
| Loch A Bhraoin | Hydro and pumped storage | 2 MW | not stated | Built |
| Three Lochs Hydro | Hydro and pumped storage | 2 MW | 30 Jun 2024 | Consents Approved |
| Garbhaig Hydro Generating Station | Hydro and pumped storage | 2 MW | not stated | Built |
| Coulags Hydro | Hydro and pumped storage | 1.5 MW | not stated | Built |
| Badachro Hydro | Hydro and pumped storage | 1.4 MW | not stated | Built |
| Taodail Hydro | Hydro and pumped storage | 1.35 MW | not stated | Built |
| Coulin Hydro | Hydro and pumped storage | 1.2 MW | not stated | Built |
Supported by National Energy SO Open Data