Harestanes West Wind Farm 132/33kV

NESO connection site, host SPT.

Contracted here0.12 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Mar 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue119.3 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Harestanes31 May 202431 Mar 202838.3 MW
Harestanes West Wind Farm31 May 20241 Sep 202956 MW
Harestanes West Wind Farm31 May 20241 Jul 203525 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2028: 38 MW2029: 94 MW2035: 119 MW20282029203020312032203320342035119 MW
0 MW100 MW200 MW2028: 38 MW2029: 94 MW2035: 119 MW2028203020322035119 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202838.3 MW
202994.3 MW
2035119.3 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Harestanes38.3 MW0 MW31 Mar 2028not statedgate not printedUnder Construction/Commissioning
2Harestanes West Wind Farm56 MW38.3 MW1 Sep 2029not statedgate not printedScoping
3Harestanes West Wind Farm25 MW94.3 MW1 Jul 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028138.3 MW
2029156 MW
2035125 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
HarestanesHybrid163.3 MW31 Mar 2028Under Construction/Commissioning
Old Forest of AeOnshore wind81 MW1 Jul 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.