Harker 400kV Substation

NESO connection site, host NGET.

Contracted here2.69 GWNot yet connected, as printed
Entries in the queue10entries with a printed MW
Earliest connection date30 Oct 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,462 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Harker Green Energy Centre31 May 202430 Oct 2028400 MW
Pivot Power Harker Hybrid31 May 202431 Oct 202957 MW
BESS Harker31 May 202430 May 2031200 MW
Harker Green Energy Centre31 May 202430 Oct 2032625 MW
RIGG HOUSE PV FARM31 May 202431 Oct 2037150 MW
Barrow20 Dec 202431 Oct 203730 MW
Harker PV & BESS Sub31 May 20241 Nov 2037249.9 MW
Low Harker BESS31 May 202430 Nov 2037400 MW
NEL Story31 May 202430 Nov 2037240 MW
ESB Harker BESS22 Jul 202531 Oct 2039342 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2028: 400 MW2029: 457 MW2031: 657 MW2032: 1.3 GW2037: 2.4 GW2039: 2.7 GW2028203020322034203620392.7 GW
0 MW2.0 GW4.0 GW2028: 400 MW2029: 457 MW2031: 657 MW2032: 1.3 GW2037: 2.4 GW2039: 2.7 GW202820312034203720392.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2028400 MW
2029457 MW
2031657 MW
20321,282 MW
20372,351.9 MW
20392,693.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Harker Green Energy Centre400 MW0 MW30 Oct 2028not statedgate not printedAwaiting Consents
2Pivot Power Harker Hybrid57 MW400 MW31 Oct 20291gate 1Scoping
3BESS Harker200 MW457 MW30 May 2031not statedgate not printedConsents Approved
4Harker Green Energy Centre625 MW657 MW30 Oct 2032not statedgate not printedAwaiting Consents
5RIGG HOUSE PV FARM150 MW1,282 MW31 Oct 2037not statedgate not printedScoping
6Barrow30 MW1,432 MW31 Oct 2037not statedgate not printedScoping
7Harker PV & BESS Sub249.9 MW1,462 MW1 Nov 20371gate 1Scoping
8Low Harker BESS400 MW1,711.9 MW30 Nov 2037not statedgate not printedScoping
9NEL Story240 MW2,111.9 MW30 Nov 20371gate 1Scoping
10ESB Harker BESS342 MW2,351.9 MW31 Oct 2039not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20281400 MW
2029157 MW
20311200 MW
20321625 MW
203751,069.9 MW
20391342 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Harker Green Energy CentreHybrid1,025 MW30 Oct 2032Awaiting Consents
Low Harker BESSHybrid400 MW30 Nov 2037Scoping
ESB Harker BESSBattery storage342 MW31 Oct 2039Scoping
Harker PV & BESS SubHybrid249.9 MW1 Nov 2037Scoping
NEL StoryBattery storage240 MW30 Nov 2037Scoping
BESS HarkerBattery storage200 MW30 May 2031Consents Approved
RIGG HOUSE PV FARMSolar150 MW31 Oct 2037Scoping
Pivot Power Harker HybridHybrid57 MW31 Oct 2029Scoping
BarrowBattery storage30 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data