The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Worset PV & BESS Park
31 May 2024 to 30 Oct 2027 (gate 2) - WORSET LANE BESS
31 May 2024 to 31 May 2029 (gate 2) - Martindale Farm
22 Jul 2025 to 30 Oct 2039 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Worset PV & BESS Park | 31 May 2024 | 30 Oct 2027 | 37.5 MW |
| WORSET LANE BESS | 31 May 2024 | 31 May 2029 | 200 MW |
| Martindale Farm | 22 Jul 2025 | 30 Oct 2039 | 239.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 37.5 MW |
| 2029 | 237.5 MW |
| 2039 | 477.4 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Worset PV & BESS Park | 37.5 MW | 0 MW | 30 Oct 2027 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | WORSET LANE BESS | 200 MW | 37.5 MW | 31 May 2029 | 2 | gate 2 | Consents Approved |
| 3 | Martindale Farm | 239.9 MW | 237.5 MW | 30 Oct 2039 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 37.5 MW |
| 2029 | 1 | 200 MW |
| 2039 | 1 | 239.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Martindale Farm | Hybrid | 239.9 MW | 30 Oct 2039 | Scoping |
| WORSET LANE BESS | Battery storage | 200 MW | 31 May 2029 | Consents Approved |
| Worset PV & BESS Park | Hybrid | 37.5 MW | 30 Oct 2027 | Under Construction/Commissioning |
| Tamar-Hartmoor | Reactive compensation | 0 MW | 31 May 2025 | Scoping |
Supported by National Energy SO Open Data