N84 Grid

Hopsrig Collector 132/33kV Substation

NESO connection site, host SPT.

Contracted here0.14 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date15 Dec 2026Date printed in the register

The queue, in order

Order calculated by N84
First in queue136 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Loganhead Windfarm31 May 202431 Oct 202736 MW
Hopsrig Wind Farm31 May 202431 Oct 202748 MW
Dealanach WLC WF31 May 202415 Dec 202612 MW
Hareshaw Rig Wind Farm31 May 202431 Oct 202940 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 12 MW2027: 96 MW2029: 136 MW2026202720282029136 MW
0 MW100 MW200 MW2026: 12 MW2027: 96 MW2029: 136 MW2026202720282029136 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202612 MW
202796 MW
2029136 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Loganhead Windfarm36 MW0 MW31 Oct 20272gate 2Consents Approved
2Hopsrig Wind Farm48 MW36 MW31 Oct 20272gate 2Consents Approved
3Dealanach WLC WF12 MW84 MW15 Dec 2026not statedgate not printedScoping
4Hareshaw Rig Wind Farm40 MW96 MW31 Oct 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026112 MW
2027284 MW
2029140 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Hopsrig Wind FarmOnshore wind48 MW31 Oct 2027Consents Approved
Hareshaw Rig Wind FarmOnshore wind40 MW31 Oct 2029Scoping
Loganhead WindfarmOnshore wind36 MW31 Oct 2027Consents Approved
Dealanach WLC WFOnshore wind12 MW15 Dec 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.