The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Loganhead Windfarm
31 May 2024 to 31 Oct 2027 (gate 2) - Hopsrig Wind Farm
31 May 2024 to 31 Oct 2027 (gate 2) - Dealanach WLC WF
31 May 2024 to 15 Dec 2026 (gate not printed) - Hareshaw Rig Wind Farm
31 May 2024 to 31 Oct 2029 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Loganhead Windfarm | 31 May 2024 | 31 Oct 2027 | 36 MW |
| Hopsrig Wind Farm | 31 May 2024 | 31 Oct 2027 | 48 MW |
| Dealanach WLC WF | 31 May 2024 | 15 Dec 2026 | 12 MW |
| Hareshaw Rig Wind Farm | 31 May 2024 | 31 Oct 2029 | 40 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2026 | 12 MW |
| 2027 | 96 MW |
| 2029 | 136 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Loganhead Windfarm | 36 MW | 0 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 2 | Hopsrig Wind Farm | 48 MW | 36 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 3 | Dealanach WLC WF | 12 MW | 84 MW | 15 Dec 2026 | not stated | gate not printed | Scoping |
| 4 | Hareshaw Rig Wind Farm | 40 MW | 96 MW | 31 Oct 2029 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2026 | 1 | 12 MW |
| 2027 | 2 | 84 MW |
| 2029 | 1 | 40 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Hopsrig Wind Farm | Onshore wind | 48 MW | 31 Oct 2027 | Consents Approved |
| Hareshaw Rig Wind Farm | Onshore wind | 40 MW | 31 Oct 2029 | Scoping |
| Loganhead Windfarm | Onshore wind | 36 MW | 31 Oct 2027 | Consents Approved |
| Dealanach WLC WF | Onshore wind | 12 MW | 15 Dec 2026 | Scoping |
Supported by National Energy SO Open Data