N84 Grid

Humber Refinery 400kV Substation

NESO connection site, host NGET.

Contracted here0.35 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date16 Jan 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue349 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • VPI Immingham B OCGT31 May 2024 to 16 Jan 2026, date already passed (gate not printed)
  • Immingham31 May 2024 to 31 Oct 2028 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
VPI Immingham B OCGT31 May 202416 Jan 2026299 MW
Immingham31 May 202431 Oct 202850 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW200 MW400 MW2026: 299 MW2028: 349 MW202620272028349 MW
0 MW200 MW400 MW2026: 299 MW2028: 349 MW202620272028349 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026299 MW
2028349 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1VPI Immingham B OCGT299 MW0 MW16 Jan 2026not statedgate not printedScoping
2Immingham50 MW299 MW31 Oct 20281gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20261299 MW
2028150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
ImminghamHybrid1,318 MW31 Oct 2028Scoping
VPI Immingham B OCGTGas299 MW16 Jan 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.