The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Bellrock Offshore Wind Farm
31 May 2024 to 31 Oct 2032 (gate not printed) - Cerulean Winds INTOG 1
20 Dec 2024 to 31 Oct 2033 (gate not printed) - Bellrock Offshore Wind Farm
31 May 2024 to 31 Oct 2035 (gate not printed) - Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm
31 May 2024 to 31 Dec 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Bellrock Offshore Wind Farm | 31 May 2024 | 31 Oct 2032 | 1,200 MW |
| Cerulean Winds INTOG 1 | 20 Dec 2024 | 31 Oct 2033 | 600 MW |
| Bellrock Offshore Wind Farm | 31 May 2024 | 31 Oct 2035 | 600 MW |
| Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm | 31 May 2024 | 31 Dec 2035 | 1,008 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2032 | 1,200 MW |
| 2033 | 1,800 MW |
| 2035 | 3,408 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Bellrock Offshore Wind Farm | 1,200 MW | 0 MW | 31 Oct 2032 | not stated | gate not printed | Scoping |
| 2 | Cerulean Winds INTOG 1 | 600 MW | 1,200 MW | 31 Oct 2033 | not stated | gate not printed | Awaiting Consents |
| 3 | Bellrock Offshore Wind Farm | 600 MW | 1,800 MW | 31 Oct 2035 | not stated | gate not printed | Scoping |
| 4 | Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm | 1,008 MW | 2,400 MW | 31 Dec 2035 | not stated | gate not printed | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2032 | 1 | 1,200 MW |
| 2033 | 1 | 600 MW |
| 2035 | 2 | 1,608 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Bellrock Offshore Wind Farm | Offshore wind | 1,800 MW | 31 Oct 2035 | Scoping |
| Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm | Offshore wind | 1,008 MW | 31 Dec 2035 | Awaiting Consents |
| Cerulean Winds INTOG 1 | Offshore wind | 600 MW | 31 Oct 2033 | Awaiting Consents |
Supported by National Energy SO Open Data