N84 Grid

Hurlie 400kV substation

NESO connection site, host SHET.

Contracted here3.41 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date31 Oct 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue3,408 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Bellrock Offshore Wind Farm31 May 202431 Oct 20321,200 MW
Cerulean Winds INTOG 120 Dec 202431 Oct 2033600 MW
Bellrock Offshore Wind Farm31 May 202431 Oct 2035600 MW
Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm31 May 202431 Dec 20351,008 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2032: 1.2 GW2033: 1.8 GW2035: 3.4 GW20322033203420353.4 GW
0 MW2.0 GW4.0 GW2032: 1.2 GW2033: 1.8 GW2035: 3.4 GW20322033203420353.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20321,200 MW
20331,800 MW
20353,408 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Bellrock Offshore Wind Farm1,200 MW0 MW31 Oct 2032not statedgate not printedScoping
2Cerulean Winds INTOG 1600 MW1,200 MW31 Oct 2033not statedgate not printedAwaiting Consents
3Bellrock Offshore Wind Farm600 MW1,800 MW31 Oct 2035not statedgate not printedScoping
4Bowdun (ex Cluaran Deas Ear) Offshore Wind Farm1,008 MW2,400 MW31 Dec 2035not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203211,200 MW
20331600 MW
203521,608 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Bellrock Offshore Wind FarmOffshore wind1,800 MW31 Oct 2035Scoping
Bowdun (ex Cluaran Deas Ear) Offshore Wind FarmOffshore wind1,008 MW31 Dec 2035Awaiting Consents
Cerulean Winds INTOG 1Offshore wind600 MW31 Oct 2033Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.