The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- IPC Grid Tremorfa
31 May 2024 to 6 Dec 2036 (gate 1) - TH Bridge Farm
31 May 2024 to 31 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| IPC Grid Tremorfa | 31 May 2024 | 6 Dec 2036 | 1,000 MW |
| TH Bridge Farm | 31 May 2024 | 31 Oct 2037 | 400 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2036 | 1,000 MW |
| 2037 | 1,400 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | IPC Grid Tremorfa | 1,000 MW | 0 MW | 6 Dec 2036 | 1 | gate 1 | Scoping |
| 2 | TH Bridge Farm | 400 MW | 1,000 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2036 | 1 | 1,000 MW |
| 2037 | 1 | 400 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| IPC Grid Tremorfa | Battery storage | 1,000 MW | 6 Dec 2036 | Scoping |
| TH Bridge Farm | Battery storage | 400 MW | 31 Oct 2037 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.