N84 Grid

Indian Queens 400kV Substation

NESO connection site, host NGET.

Contracted here0.58 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Jul 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue579.5 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Indian Queens Energy Centre31 May 202430 May 202747.5 MW
Indian Queens31 May 202430 Jul 202447.5 MW
St Dennis Hendra31 May 202431 Oct 202447.5 MW
Indian Queens31 May 202431 Oct 2031437 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2024: 95 MW2027: 143 MW2031: 580 MW20242025202620272028202920302031580 MW
0 MW400 MW800 MW2024: 95 MW2027: 143 MW2031: 580 MW2024202620282031580 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202495 MW
2027142.5 MW
2031579.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Indian Queens Energy Centre47.5 MW0 MW30 May 20272gate 2Consents Approved
2Indian Queens47.5 MW47.5 MW30 Jul 2024not statedgate not printedConsents Approved
3St Dennis Hendra47.5 MW95 MW31 Oct 2024not statedgate not printedConsents Approved
4Indian Queens437 MW142.5 MW31 Oct 20311gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024295 MW
2027147.5 MW
20311437 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Indian Queens (GRIDMOVE LTD)Hybrid437 MW31 Oct 2031Scoping
Indian Queens (INDIAN QUEENS POWER LIMITED)Gas140 MWnot statedBuilt
Indian Queens (PIVOTED POWER LLP)Battery storage47.5 MW30 Jul 2024Consents Approved
St Dennis HendraBattery storage47.5 MW31 Oct 2024Consents Approved
Indian Queens Energy CentreHybrid47.5 MW30 May 2027Consents Approved

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.