N84 Grid

Inverkeithing 132/33kV

NESO connection site, host SPT.

Contracted here0.14 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date1 Jan 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue136.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Balbougie Energy Centre31 May 202431 Jul 202642 MW
Inverkeithing Gas Generation7 Nov 20251 Jan 202420 MW
Aberdour Solar Farm7 Nov 202530 Jun 202625 MW
STOR Field 9 BESS31 May 202430 Jul 202949.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2024: 20 MW2026: 87 MW2029: 137 MW202420252026202720282029137 MW
0 MW100 MW200 MW2024: 20 MW2026: 87 MW2029: 137 MW2024202620282029137 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202420 MW
202687 MW
2029136.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Balbougie Energy Centre42 MW0 MW31 Jul 20262gate 2Consents Approved
2Inverkeithing Gas Generation20 MW42 MW1 Jan 2024not statedgate not printedScoping
3Aberdour Solar Farm25 MW62 MW30 Jun 2026not statedgate not printedScoping
4STOR Field 9 BESS49.9 MW87 MW30 Jul 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2024120 MW
2026267 MW
2029149.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
STOR Field 9 BESSBattery storage49.9 MW30 Jul 2029Scoping
Balbougie Energy CentreBattery storage42 MW31 Jul 2026Consents Approved
Aberdour Solar FarmSolar25 MW30 Jun 2026Scoping
Inverkeithing Gas GenerationGas20 MW1 Jan 2024Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.