The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Ironbridge Green Energy Centre
31 May 2024 to 30 Oct 2029 (gate 1) - Ironbridge
31 May 2024 to 30 Apr 2031 (gate not printed) - ELMYA REDNAL
31 May 2024 to 30 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Ironbridge Green Energy Centre | 31 May 2024 | 30 Oct 2029 | 400 MW |
| Ironbridge | 31 May 2024 | 30 Apr 2031 | 600 MW |
| ELMYA REDNAL | 31 May 2024 | 30 Oct 2034 | 300 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2029 | 400 MW |
| 2031 | 1,000 MW |
| 2034 | 1,300 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Ironbridge Green Energy Centre | 400 MW | 0 MW | 30 Oct 2029 | 1 | gate 1 | Awaiting Consents |
| 2 | Ironbridge | 600 MW | 400 MW | 30 Apr 2031 | not stated | gate not printed | Scoping |
| 3 | ELMYA REDNAL | 300 MW | 1,000 MW | 30 Oct 2034 | 1 | gate 1 | Awaiting Consents |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2029 | 1 | 400 MW |
| 2031 | 1 | 600 MW |
| 2034 | 1 | 300 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Ironbridge (IGP SOLAR 16 LIMITED) | Hybrid | 600 MW | 30 Apr 2031 | Scoping |
| Ironbridge Green Energy Centre | Hybrid | 400 MW | 30 Oct 2029 | Awaiting Consents |
| ELMYA REDNAL | Battery storage | 300 MW | 30 Oct 2034 | Awaiting Consents |
| Ironbridge - New Connection | Hybrid | 0 MW | 30 Dec 2026 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.