Keadby 400kV Substation

NESO connection site, host NGET.

Contracted here1.14 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,142 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Keadby North Power Station31 May 202431 Oct 2031892 MW
Keadby31 May 202431 Oct 2033250 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2031: 892 MW2033: 1.1 GW2031203220331.1 GW
0 MW1.0 GW2.0 GW2031: 892 MW2033: 1.1 GW2031203220331.1 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031892 MW
20331,142 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Keadby North Power Station892 MW0 MW31 Oct 2031not statedgate not printedAwaiting Consents
2Keadby250 MW892 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311892 MW
20331250 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Keadby (Keadby Generation Limited)Gas910 MWnot statedBuilt
Keadby South Power StationGas910 MW30 Apr 2034Built
Keadby IIGas893 MWnot statedBuilt
Keadby North Power StationGas892 MW31 Oct 2031Awaiting Consents
Keadby (ONE PLANET DEVELOPMENTS LIMITED)Battery storage250 MW31 Oct 2033Scoping
BriggGas99 MWnot statedBuilt
GlanfordBiomass and waste15 MWnot statedBuilt
Keadby GSP (NORTHERN POWERGRID (YORKSHIRE) PLC)Hybrid0 MWnot statedScoping

Supported by National Energy SO Open Data