Kemsley 400kV Substation

NESO connection site, host NGET.

Contracted here1.75 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date27 Oct 2027Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,748.9 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Ouse Energy Storage31 May 202427 Oct 2027249 MW
Cronos15 Feb 202231 Oct 20291,400 MW
Barge Way 120MW BESS31 May 202431 Oct 203399.9 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2027: 249 MW2029: 1.6 GW2033: 1.7 GW20272028202920302031203220331.7 GW
0 MW1.0 GW2.0 GW2027: 249 MW2029: 1.6 GW2033: 1.7 GW20272029203120331.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2027249 MW
20291,649 MW
20331,748.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Ouse Energy Storage249 MW0 MW27 Oct 2027not statedgate not printedScoping
2Cronos1,400 MW249 MW31 Oct 2029not statedgate not printedScoping
3Barge Way 120MW BESS99.9 MW1,649 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Interconnector Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20271249 MW
202911,400 MW
2033199.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
CronosInterconnector1,400 MW31 Oct 2029Scoping
Ouse Energy StorageBattery storage249 MW27 Oct 2027Scoping
Barge Way 120MW BESSBattery storage99.9 MW31 Oct 2033Scoping
Kemsley (PIVOTED POWER LLP)Battery storage49.9 MWnot statedBuilt
Kemsley (GROVEHURST ENERGY LIMITED)Gas35.8 MWnot statedBuilt
Ridham Battery StorageBattery storage0 MW31 Oct 2031Scoping

Supported by National Energy SO Open Data