The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Lochfauld Solar Park
7 Nov 2025 to 30 Jun 2025, date already passed (gate not printed) - Cleveden Road BESS
31 May 2024 to 30 Jun 2031 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Lochfauld Solar Park | 7 Nov 2025 | 30 Jun 2025 | 18.4 MW |
| Cleveden Road BESS | 31 May 2024 | 30 Jun 2031 | 43 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 18.4 MW |
| 2031 | 61.4 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Lochfauld Solar Park | 18.4 MW | 0 MW | 30 Jun 2025 | not stated | gate not printed | Scoping |
| 2 | Cleveden Road BESS | 43 MW | 18.4 MW | 30 Jun 2031 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 18.4 MW |
| 2031 | 1 | 43 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Cleveden Road BESS | Battery storage | 43 MW | 30 Jun 2031 | Scoping |
| Lochfauld Solar Park | Solar | 18.4 MW | 30 Jun 2025 | Scoping |
| Balmore WTW | Solar | 5.15 MW | not stated | Built |
| Summerston PV 50MW | Solar | 0 MW | not stated | Scoping |