N84 Grid

Kilmarnock South 275/33kV

NESO connection site, host SPT.

Contracted here0.57 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Oct 2022Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue571.13 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Mill Rig Wind Farm7 Nov 202528 Apr 202634.2 MW
Kilmarnock South Battery Storage31 May 202430 Apr 2027500 MW
Bankend Rig Extension Wind Farm7 Nov 202531 Oct 20226.9 MW
Shewalton Rd Solar Farm7 Nov 202525 Oct 20245.03 MW
Doveryard Energy Centre7 Nov 202519 May 202525 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW400 MW800 MW2022: 7 MW2024: 12 MW2025: 37 MW2026: 71 MW2027: 571 MW202220232024202520262027571 MW
0 MW400 MW800 MW2022: 7 MW2024: 12 MW2025: 37 MW2026: 71 MW2027: 571 MW2022202420262027571 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20226.9 MW
202411.93 MW
202536.93 MW
202671.13 MW
2027571.13 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Mill Rig Wind Farm34.2 MW0 MW28 Apr 20262gate 2Under Construction/Commissioning
2Kilmarnock South Battery Storage500 MW34.2 MW30 Apr 20272gate 2Consents Approved
3Bankend Rig Extension Wind Farm6.9 MW534.2 MW31 Oct 2022not statedgate not printedScoping
4Shewalton Rd Solar Farm5.03 MW541.1 MW25 Oct 2024not statedgate not printedScoping
5Doveryard Energy Centre25 MW546.13 MW19 May 2025not statedgate not printedConsents Approved

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202216.9 MW
202415.03 MW
2025125 MW
2026134.2 MW
20271500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Kilmarnock South Battery StorageBattery storage500 MW30 Apr 2027Consents Approved
Zenobe Kilmarnock SouthBattery storage300 MWnot statedBuilt
Mill Rig Wind FarmOnshore wind34.2 MW28 Apr 2026Under Construction/Commissioning
Doveryard Energy CentreBiomass and waste25 MW19 May 2025Consents Approved
Bankend Rig Extension Wind FarmOnshore wind6.9 MW31 Oct 2022Scoping
Shewalton Rd Solar FarmSolar5.03 MW25 Oct 2024Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.