The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Mill Rig Wind Farm
7 Nov 2025 to 28 Apr 2026, date already passed (gate 2) - Kilmarnock South Battery Storage
31 May 2024 to 30 Apr 2027 (gate 2) - Bankend Rig Extension Wind Farm
7 Nov 2025 to 31 Oct 2022, date already passed (gate not printed) - Shewalton Rd Solar Farm
7 Nov 2025 to 25 Oct 2024, date already passed (gate not printed) - Doveryard Energy Centre
7 Nov 2025 to 19 May 2025, date already passed (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Mill Rig Wind Farm | 7 Nov 2025 | 28 Apr 2026 | 34.2 MW |
| Kilmarnock South Battery Storage | 31 May 2024 | 30 Apr 2027 | 500 MW |
| Bankend Rig Extension Wind Farm | 7 Nov 2025 | 31 Oct 2022 | 6.9 MW |
| Shewalton Rd Solar Farm | 7 Nov 2025 | 25 Oct 2024 | 5.03 MW |
| Doveryard Energy Centre | 7 Nov 2025 | 19 May 2025 | 25 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2022 | 6.9 MW |
| 2024 | 11.93 MW |
| 2025 | 36.93 MW |
| 2026 | 71.13 MW |
| 2027 | 571.13 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Mill Rig Wind Farm | 34.2 MW | 0 MW | 28 Apr 2026 | 2 | gate 2 | Under Construction/Commissioning |
| 2 | Kilmarnock South Battery Storage | 500 MW | 34.2 MW | 30 Apr 2027 | 2 | gate 2 | Consents Approved |
| 3 | Bankend Rig Extension Wind Farm | 6.9 MW | 534.2 MW | 31 Oct 2022 | not stated | gate not printed | Scoping |
| 4 | Shewalton Rd Solar Farm | 5.03 MW | 541.1 MW | 25 Oct 2024 | not stated | gate not printed | Scoping |
| 5 | Doveryard Energy Centre | 25 MW | 546.13 MW | 19 May 2025 | not stated | gate not printed | Consents Approved |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2022 | 1 | 6.9 MW |
| 2024 | 1 | 5.03 MW |
| 2025 | 1 | 25 MW |
| 2026 | 1 | 34.2 MW |
| 2027 | 1 | 500 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Kilmarnock South Battery Storage | Battery storage | 500 MW | 30 Apr 2027 | Consents Approved |
| Zenobe Kilmarnock South | Battery storage | 300 MW | not stated | Built |
| Mill Rig Wind Farm | Onshore wind | 34.2 MW | 28 Apr 2026 | Under Construction/Commissioning |
| Doveryard Energy Centre | Biomass and waste | 25 MW | 19 May 2025 | Consents Approved |
| Bankend Rig Extension Wind Farm | Onshore wind | 6.9 MW | 31 Oct 2022 | Scoping |
| Shewalton Rd Solar Farm | Solar | 5.03 MW | 25 Oct 2024 | Scoping |