Knocknagael 132kV Substation

NESO connection site, host SHET.

Contracted here0.90 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date30 Apr 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue900 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Loch na Cathrach Pumped Storage Hydro31 May 202430 Apr 2029450 MW
Knocknagael BESS31 May 202430 Jul 2029200 MW
Loch na Cathrach Pumped Storage Hydro31 May 202431 Oct 2030100 MW
Balrobert Farm BESS20 Dec 202431 Oct 2032150 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2029: 650 MW2030: 750 MW2032: 900 MW2029203020312032900 MW
0 MW500 MW1.0 GW2029: 650 MW2030: 750 MW2032: 900 MW2029203020312032900 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029650 MW
2030750 MW
2032900 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Loch na Cathrach Pumped Storage Hydro450 MW0 MW30 Apr 2029not statedgate not printedConsents Approved
2Knocknagael BESS200 MW450 MW30 Jul 20291gate 1Awaiting Consents
3Loch na Cathrach Pumped Storage Hydro100 MW650 MW31 Oct 2030not statedgate not printedConsents Approved
4Balrobert Farm BESS150 MW750 MW31 Oct 20321gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20292650 MW
20301100 MW
20321150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Red John PSHHydro and pumped storage550 MW31 Oct 2030Consents Approved
Knocknagael BESSBattery storage200 MW30 Jul 2029Awaiting Consents
Balrobert Farm BESSBattery storage150 MW31 Oct 2032Scoping
Leys Energy StorageBattery storage0 MW31 Oct 2032Scoping

Supported by National Energy SO Open Data