N84 Grid

Lackenby 400kV Substation

NESO connection site, host NGET.

Contracted here1.80 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date1 Apr 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,800 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Dogger Bank Project C31 May 20241 Apr 20251,200 MW
Crathorne Estate BESS and Solar Farm20 Dec 202430 Oct 2035600 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2025: 1.2 GW2035: 1.8 GW2025202720292031203320351.8 GW
0 MW1.0 GW2.0 GW2025: 1.2 GW2035: 1.8 GW20252028203120351.8 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20251,200 MW
20351,800 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Dogger Bank Project C1,200 MW0 MW1 Apr 2025not statedgate not printedConsents Approved
2Crathorne Estate BESS and Solar Farm600 MW1,200 MW30 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202511,200 MW
20351600 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Sofia Offshore Wind FarmOffshore wind1,320 MWnot statedBuilt
Dogger Bank Project COffshore wind1,200 MW1 Apr 2025Consents Approved
Crathorne Estate BESS and Solar FarmHybrid600 MW30 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.