N84 Grid

Laleham 132kV Substation

NESO connection site, host NGET.

Contracted here0.09 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 May 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue90 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Laleham31 May 2024 to 30 May 2028 (gate 1)
  • Laleham31 May 2024 to 31 Oct 2030 (gate 1)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Laleham31 May 202430 May 202849.9 MW
Laleham31 May 202431 Oct 203040.1 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2028: 50 MW2030: 90 MW20282029203090 MW
0 MW50 MW100 MW2028: 50 MW2030: 90 MW20282029203090 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.9 MW
203090 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Laleham49.9 MW0 MW30 May 20281gate 1Scoping
2Laleham40.1 MW49.9 MW31 Oct 20301gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.9 MW
2030140.1 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Laleham (Juniper Energy Limited)Battery storage90 MW31 Oct 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.