The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- NatPower Penrith Green Energy Park
31 May 2024 to 30 Oct 2037 (gate 1) - Middleshaw BESS
22 Jul 2025 to 30 Oct 2037 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| NatPower Penrith Green Energy Park | 31 May 2024 | 30 Oct 2037 | 1,000 MW |
| Middleshaw BESS | 22 Jul 2025 | 30 Oct 2037 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2037 | 1,200 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | NatPower Penrith Green Energy Park | 1,000 MW | 0 MW | 30 Oct 2037 | 1 | gate 1 | Scoping |
| 2 | Middleshaw BESS | 200 MW | 1,000 MW | 30 Oct 2037 | not stated | gate not printed | Consents Approved |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2037 | 2 | 1,200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| NatPower Penrith Green Energy Park | Battery storage | 1,000 MW | 30 Oct 2037 | Scoping |
| Middleshaw BESS | Battery storage | 200 MW | 30 Oct 2037 | Consents Approved |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.