Landulph 400kV Substation

NESO connection site, host NGET.

Contracted here0.06 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date18 May 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue57 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Landulph31 May 2024 to 18 May 2026, date already passed (gate not printed)
  • Landulph31 May 2024 to 31 Oct 2028 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Landulph31 May 202418 May 202649.9 MW
Landulph31 May 202431 Oct 20287.1 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2026: 50 MW2028: 57 MW20262027202857 MW
0 MW40 MW80 MW2026: 50 MW2028: 57 MW20262027202857 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202649.9 MW
202857 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Landulph49.9 MW0 MW18 May 2026not statedgate not printedConsents Approved
2Landulph7.1 MW49.9 MW31 Oct 2028not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026149.9 MW
202817.1 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Landulph (PIVOTED POWER LLP)Hybrid57 MW31 Oct 2028Scoping
Plymouth MainGas25.52 MWnot statedBuilt
Plymouth RockGas15.08 MWnot statedBuilt
TINZ Project Nene 1 (Landulph)Reactive compensation0 MW1 Apr 2025Scoping
Tamar-LandulphReactive compensation0 MW31 Oct 2025Scoping
Zenobe Landulph BESSBattery storage0 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data