N84 Grid

Langage 400kV Substation

NESO connection site, host NGET.

Contracted here1.65 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date30 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,649 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Langage Battery Storage31 May 202430 Oct 2031249 MW
Langage 40031 May 202419 Dec 2036200 MW
Langage 40031 May 202431 Oct 2037100 MW
Langage Farm31 May 202419 Dec 20371,000 MW
Langage 40031 May 202431 Oct 2038100 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2031: 249 MW2036: 449 MW2037: 1.5 GW2038: 1.6 GW203120322033203420352036203720381.6 GW
0 MW1.0 GW2.0 GW2031: 249 MW2036: 449 MW2037: 1.5 GW2038: 1.6 GW20312033203520381.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031249 MW
2036449 MW
20371,549 MW
20381,649 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Langage Battery Storage249 MW0 MW30 Oct 2031not statedgate not printedScoping
2Langage 400200 MW249 MW19 Dec 20361gate 1Scoping
3Langage 400100 MW449 MW31 Oct 20371gate 1Scoping
4Langage Farm1,000 MW549 MW19 Dec 20371gate 1Scoping
5Langage 400100 MW1,549 MW31 Oct 20381gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311249 MW
20361200 MW
203721,100 MW
20381100 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Langage FarmHybrid1,000 MW19 Dec 2037Scoping
Langage (EP LANGAGE LIMITED)Gas905 MWnot statedBuilt
Langage 400 (ENSO GREEN HOLDINGS LIMITED)Hybrid400 MW31 Oct 2038Scoping
Langage Battery StorageBattery storage249 MW30 Oct 2031Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.