N84 Grid

Leeds North Connection Node C 400kV Substation

NESO connection site, host NGET.

Contracted here2.97 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date31 Oct 2033Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,630 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
FCC Thurcroft BESS31 May 202431 Oct 2033750 MW
NEL Bluebell31 May 202430 Oct 2035240 MW
Ferrybridge B - NEL Hunter31 May 202430 Oct 2035200 MW
NEL Springfield31 May 202430 Oct 2035240 MW
West Melton PV & BESS Station31 May 202430 Oct 2035200 MW
Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)22 Jul 202530 Oct 20351,000 MW
Fryston Lane 100MW BESS31 May 202431 Oct 2035100 MW
NEL Conway222 Jul 202531 Oct 2035240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2033: 750 MW2035: 3.0 GW2033203420353.0 GW
0 MW2.0 GW4.0 GW2033: 750 MW2035: 3.0 GW2033203420353.0 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2033750 MW
20352,970 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1FCC Thurcroft BESS750 MW0 MW31 Oct 20331gate 1Scoping
2NEL Bluebell240 MW750 MW30 Oct 2035not statedgate not printedScoping
3Ferrybridge B - NEL Hunter200 MW990 MW30 Oct 2035not statedgate not printedScoping
4NEL Springfield240 MW1,190 MW30 Oct 2035not statedgate not printedScoping
5West Melton PV & BESS Station200 MW1,430 MW30 Oct 20351gate 1Scoping
6Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)1,000 MW1,630 MW30 Oct 20351gate 1Scoping
7Fryston Lane 100MW BESS100 MW2,630 MW31 Oct 20351gate 1Scoping
8NEL Conway2240 MW2,730 MW31 Oct 20351gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20331750 MW
203572,220 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)Hybrid1,000 MW30 Oct 2035Scoping
FCC Thurcroft BESSBattery storage750 MW31 Oct 2033Scoping
NEL SpringfieldBattery storage240 MW30 Oct 2035Scoping
NEL BluebellBattery storage240 MW30 Oct 2035Scoping
NEL Conway2Battery storage240 MW31 Oct 2035Scoping
Ferrybridge B - NEL HunterBattery storage200 MW30 Oct 2035Scoping
West Melton PV & BESS StationHybrid200 MW30 Oct 2035Scoping
Fryston Lane 100MW BESSBattery storage100 MW31 Oct 2035Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.