The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- FCC Thurcroft BESS
31 May 2024 to 31 Oct 2033 (gate 1) - NEL Bluebell
31 May 2024 to 30 Oct 2035 (gate not printed) - Ferrybridge B - NEL Hunter
31 May 2024 to 30 Oct 2035 (gate not printed) - NEL Springfield
31 May 2024 to 30 Oct 2035 (gate not printed) - West Melton PV & BESS Station
31 May 2024 to 30 Oct 2035 (gate 1) - Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)
22 Jul 2025 to 30 Oct 2035 (gate 1) - Fryston Lane 100MW BESS
31 May 2024 to 31 Oct 2035 (gate 1) - NEL Conway2
22 Jul 2025 to 31 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| FCC Thurcroft BESS | 31 May 2024 | 31 Oct 2033 | 750 MW |
| NEL Bluebell | 31 May 2024 | 30 Oct 2035 | 240 MW |
| Ferrybridge B - NEL Hunter | 31 May 2024 | 30 Oct 2035 | 200 MW |
| NEL Springfield | 31 May 2024 | 30 Oct 2035 | 240 MW |
| West Melton PV & BESS Station | 31 May 2024 | 30 Oct 2035 | 200 MW |
| Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH) | 22 Jul 2025 | 30 Oct 2035 | 1,000 MW |
| Fryston Lane 100MW BESS | 31 May 2024 | 31 Oct 2035 | 100 MW |
| NEL Conway2 | 22 Jul 2025 | 31 Oct 2035 | 240 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2033 | 750 MW |
| 2035 | 2,970 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | FCC Thurcroft BESS | 750 MW | 0 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 2 | NEL Bluebell | 240 MW | 750 MW | 30 Oct 2035 | not stated | gate not printed | Scoping |
| 3 | Ferrybridge B - NEL Hunter | 200 MW | 990 MW | 30 Oct 2035 | not stated | gate not printed | Scoping |
| 4 | NEL Springfield | 240 MW | 1,190 MW | 30 Oct 2035 | not stated | gate not printed | Scoping |
| 5 | West Melton PV & BESS Station | 200 MW | 1,430 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 6 | Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH) | 1,000 MW | 1,630 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 7 | Fryston Lane 100MW BESS | 100 MW | 2,630 MW | 31 Oct 2035 | 1 | gate 1 | Scoping |
| 8 | NEL Conway2 | 240 MW | 2,730 MW | 31 Oct 2035 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2033 | 1 | 750 MW |
| 2035 | 7 | 2,220 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH) | Hybrid | 1,000 MW | 30 Oct 2035 | Scoping |
| FCC Thurcroft BESS | Battery storage | 750 MW | 31 Oct 2033 | Scoping |
| NEL Springfield | Battery storage | 240 MW | 30 Oct 2035 | Scoping |
| NEL Bluebell | Battery storage | 240 MW | 30 Oct 2035 | Scoping |
| NEL Conway2 | Battery storage | 240 MW | 31 Oct 2035 | Scoping |
| Ferrybridge B - NEL Hunter | Battery storage | 200 MW | 30 Oct 2035 | Scoping |
| West Melton PV & BESS Station | Hybrid | 200 MW | 30 Oct 2035 | Scoping |
| Fryston Lane 100MW BESS | Battery storage | 100 MW | 31 Oct 2035 | Scoping |