The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Tewitt Farm BESS
31 May 2024 to 30 Oct 2035 (gate 1) - BlackDyke BESS
20 Dec 2024 to 31 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Tewitt Farm BESS | 31 May 2024 | 30 Oct 2035 | 200 MW |
| BlackDyke BESS | 20 Dec 2024 | 31 Oct 2035 | 250 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2035 | 450 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Tewitt Farm BESS | 200 MW | 0 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 2 | BlackDyke BESS | 250 MW | 200 MW | 31 Oct 2035 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2035 | 2 | 450 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| BlackDyke BESS | Battery storage | 250 MW | 31 Oct 2035 | Scoping |
| Tewitt Farm BESS | Battery storage | 200 MW | 30 Oct 2035 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.