The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Longhill Burn Wind Farm
7 Nov 2025 to 31 Oct 2022, date already passed (gate not printed) - Selms Muir Solar & Battery Storage
7 Nov 2025 to 31 Jul 2026, date already passed (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Longhill Burn Wind Farm | 7 Nov 2025 | 31 Oct 2022 | 50 MW |
| Selms Muir Solar & Battery Storage | 7 Nov 2025 | 31 Jul 2026 | 6 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2022 | 50 MW |
| 2026 | 56 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Longhill Burn Wind Farm | 50 MW | 0 MW | 31 Oct 2022 | not stated | gate not printed | Consents Approved |
| 2 | Selms Muir Solar & Battery Storage | 6 MW | 50 MW | 31 Jul 2026 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2022 | 1 | 50 MW |
| 2026 | 1 | 6 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Harburnhead Wind Farm | Onshore wind | 51.7 MW | not stated | Built |
| Longhill Burn Wind Farm | Onshore wind | 50 MW | 31 Oct 2022 | Consents Approved |
| Pearie Law Wind Farm | Onshore wind | 19.2 MW | not stated | Built |
| Muirhall Extension II Wind Farm | Onshore wind | 9.6 MW | not stated | Built |
| Muirhall Wind Farm Extension | Onshore wind | 7 MW | not stated | Built |
| Selms Muir Solar & Battery Storage | Hybrid | 6 MW | 31 Jul 2026 | Scoping |
Supported by National Energy SO Open Data