The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Amersham Main
31 May 2024 to 31 Oct 2037 (gate 1) - Amersham Substation
31 May 2024 to 31 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Amersham Main | 31 May 2024 | 31 Oct 2037 | 1,000 MW |
| Amersham Substation | 31 May 2024 | 31 Oct 2037 | 200 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2037 | 1,200 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Amersham Main | 1,000 MW | 0 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 2 | Amersham Substation | 200 MW | 1,000 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2037 | 2 | 1,200 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Amersham Main | Hybrid | 1,000 MW | 31 Oct 2037 | Scoping |
| Amersham Substation | Battery storage | 200 MW | 31 Oct 2037 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.