N84 Grid

Longside 400kV Substation

NESO connection site, host SHET.

Contracted here5.70 GWNot yet connected, as printed
Entries in the queue8entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue5,100 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Marram Wind Offshore Wind Farm31 May 202431 Oct 20311,000 MW
Marram Wind Offshore Wind Farm31 May 202431 Oct 20332,000 MW
Muir Mhor Offshore Wind Farm31 May 202431 Oct 20331,000 MW
Broadshore Offshore Wind Farm31 May 202431 Oct 2033900 MW
Scaraben Offshore Wind Farm31 May 202431 Oct 2033100 MW
Sinclair Offshore Wind Farm31 May 202431 Oct 2033100 MW
Netherton BESS22 Jul 202531 Oct 2033400 MW
Netherton Hub Bess20 Dec 202431 Oct 2033200 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW4.0 GW8.0 GW2031: 1.0 GW2033: 5.7 GW2031203220335.7 GW
0 MW4.0 GW8.0 GW2031: 1.0 GW2033: 5.7 GW2031203220335.7 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20311,000 MW
20335,700 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Marram Wind Offshore Wind Farm1,000 MW0 MW31 Oct 2031not statedgate not printedScoping
2Marram Wind Offshore Wind Farm2,000 MW1,000 MW31 Oct 2033not statedgate not printedScoping
3Muir Mhor Offshore Wind Farm1,000 MW3,000 MW31 Oct 2033not statedgate not printedAwaiting Consents
4Broadshore Offshore Wind Farm900 MW4,000 MW31 Oct 2033not statedgate not printedScoping
5Scaraben Offshore Wind Farm100 MW4,900 MW31 Oct 2033not statedgate not printedScoping
6Sinclair Offshore Wind Farm100 MW5,000 MW31 Oct 2033not statedgate not printedScoping
7Netherton BESS400 MW5,100 MW31 Oct 20331gate 1Scoping
8Netherton Hub Bess200 MW5,500 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203111,000 MW
203374,700 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
OWF3Offshore wind3,000 MW31 Oct 2033Scoping
Muir Mhor Offshore Wind FarmOffshore wind1,000 MW31 Oct 2033Awaiting Consents
Broadshore Offshore Wind FarmOffshore wind900 MW31 Oct 2033Scoping
Netherton BESSBattery storage400 MW31 Oct 2033Scoping
Netherton Hub BessBattery storage200 MW31 Oct 2033Scoping
Sinclair Offshore Wind FarmOffshore wind100 MW31 Oct 2033Scoping
Scaraben Offshore Wind FarmOffshore wind100 MW31 Oct 2033Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.