N84 Grid

Lorg Wind Farm 132/32kV

NESO connection site, host SPT.

Contracted here0.07 GWNot yet connected, as printed
Entries in the queue1entry with a printed MW
Earliest connection date7 Apr 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue69.5 MW across the first project
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • Lorg Wind Farm31 May 2024 to 7 Apr 2028 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lorg Wind Farm31 May 20247 Apr 202869.5 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2028: 70 MW202870 MW
0 MW40 MW80 MW2028: 70 MW202870 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202869.5 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lorg Wind Farm69.5 MW0 MW7 Apr 2028not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028169.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Lorg Wind Farm (RWE Renewables UK Onshore Wind Limited)Onshore wind69.5 MW7 Apr 2028Awaiting Consents

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.