N84 Grid

Lovedean 400kV Substation

NESO connection site, host NGET.

Contracted here2.36 GWNot yet connected, as printed
Entries in the queue4entries with a printed MW
Earliest connection date1 Jun 2028Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,355.9 MW across the first 4 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Lovedean Greener Grid Park31 May 20241 Jun 202849.9 MW
Lovedean (Tertiary)31 May 202430 Oct 202957 MW
Aquind Interconnector15 Feb 202231 Dec 20302,000 MW
EcoLovedean31 May 202431 Mar 2031249 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2028: 50 MW2029: 107 MW2030: 2.1 GW2031: 2.4 GW20282029203020312.4 GW
0 MW1.3 GW2.5 GW2028: 50 MW2029: 107 MW2030: 2.1 GW2031: 2.4 GW20282029203020312.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202849.9 MW
2029106.9 MW
20302,106.9 MW
20312,355.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Lovedean Greener Grid Park49.9 MW0 MW1 Jun 20281gate 1Scoping
2Lovedean (Tertiary)57 MW49.9 MW30 Oct 2029not statedgate not printedScoping
3Aquind Interconnector2,000 MW106.9 MW31 Dec 2030not statedgate not printedAwaiting Consents
4EcoLovedean249 MW2,106.9 MW31 Mar 20311gate 1Scoping

Receipt: MW and dates as printed in the NESO Interconnector Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2028149.9 MW
2029157 MW
203012,000 MW
20311249 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Aquind InterconnectorInterconnector2,000 MW31 Dec 2030Awaiting Consents
EcoLovedeanBattery storage249 MW31 Mar 2031Scoping
Lovedean (Tertiary)Hybrid57 MW30 Oct 2029Scoping
Lovedean Greener Grid ParkBattery storage49.9 MW1 Jun 2028Scoping
Peak Gen HavantGas21 MWnot statedBuilt
Green Frog @ Down Barn FarmGas20 MWnot statedBuilt

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.