M74 West Wind Farm 132kV

NESO connection site, host SPT.

Contracted here0.18 GWNot yet connected, as printed
Entries in the queue1entry with a printed MW
Earliest connection date31 Oct 2029Date printed in the register

The queue, in order

Order calculated by N84
First in queue180 MW across the first project
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

  • M74 West Wind Farm31 May 2024 to 31 Oct 2029 (gate not printed)
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
M74 West Wind Farm31 May 202431 Oct 2029180 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2029: 180 MW2029180 MW
0 MW100 MW200 MW2029: 180 MW2029180 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2029180 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1M74 West Wind Farm180 MW0 MW31 Oct 2029not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20291180 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
M74 West Wind Farm (RENEWCO POWER LIMITED)Hybrid180 MW31 Oct 2029Scoping

Supported by National Energy SO Open Data