N84 Grid

Macduff GSP

NESO connection site, host SHET.

Contracted here0.23 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date20 Jul 2023Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue181.9 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Mount Blairy7 Nov 202531 Oct 202735.2 MW
Macduff Battery Storage7 Nov 202530 Jun 202849.9 MW
Brackenhills Wind7 Nov 202520 Jul 20232.3 MW
Carlincraig Wind7 Nov 202530 Sep 20234.6 MW
Denhead Solar Farm7 Nov 202531 Mar 202920 MW
Boyndie Solar7 Nov 202530 Sep 202969.9 MW
YAMAL BESS22 Jul 202531 Oct 203350 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW125 MW250 MW2023: 7 MW2027: 42 MW2028: 92 MW2029: 182 MW2033: 232 MW202320252027202920312033232 MW
0 MW125 MW250 MW2023: 7 MW2027: 42 MW2028: 92 MW2029: 182 MW2033: 232 MW2023202620292033232 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20236.9 MW
202742.1 MW
202892 MW
2029181.9 MW
2033231.9 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Mount Blairy35.2 MW0 MW31 Oct 20272gate 2Scoping
2Macduff Battery Storage49.9 MW35.2 MW30 Jun 20282gate 2Consents Approved
3Brackenhills Wind2.3 MW85.1 MW20 Jul 2023not statedgate not printedScoping
4Carlincraig Wind4.6 MW87.4 MW30 Sep 2023not statedgate not printedConsents Approved
5Denhead Solar Farm20 MW92 MW31 Mar 2029not statedgate not printedScoping
6Boyndie Solar69.9 MW112 MW30 Sep 2029not statedgate not printedScoping
7YAMAL BESS50 MW181.9 MW31 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202326.9 MW
2027135.2 MW
2028149.9 MW
2029289.9 MW
2033150 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Boyndie SolarHybrid69.9 MW30 Sep 2029Scoping
YAMAL BESSBattery storage50 MW31 Oct 2033Scoping
Macduff Battery StorageBattery storage49.9 MW30 Jun 2028Consents Approved
Mount BlairySolar35.2 MW31 Oct 2027Scoping
Denhead Solar FarmSolar20 MW31 Mar 2029Scoping
Carlincraig WindOnshore wind4.6 MW30 Sep 2023Consents Approved
Milton of Fisherie Wind Generating StationOnshore wind4.6 MWnot statedBuilt
Easter Melrose Wind Generating StationOnshore wind2.7 MWnot statedBuilt
Gawnsmoss Wind Generating StationOnshore wind2.4 MWnot statedBuilt
Brackenhills WindOnshore wind2.3 MW20 Jul 2023Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.