The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Mount Blairy
7 Nov 2025 to 31 Oct 2027 (gate 2) - Macduff Battery Storage
7 Nov 2025 to 30 Jun 2028 (gate 2) - Brackenhills Wind
7 Nov 2025 to 20 Jul 2023, date already passed (gate not printed) - Carlincraig Wind
7 Nov 2025 to 30 Sep 2023, date already passed (gate not printed) - Denhead Solar Farm
7 Nov 2025 to 31 Mar 2029 (gate not printed) - Boyndie Solar
7 Nov 2025 to 30 Sep 2029 (gate not printed) - YAMAL BESS
22 Jul 2025 to 31 Oct 2033 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Mount Blairy | 7 Nov 2025 | 31 Oct 2027 | 35.2 MW |
| Macduff Battery Storage | 7 Nov 2025 | 30 Jun 2028 | 49.9 MW |
| Brackenhills Wind | 7 Nov 2025 | 20 Jul 2023 | 2.3 MW |
| Carlincraig Wind | 7 Nov 2025 | 30 Sep 2023 | 4.6 MW |
| Denhead Solar Farm | 7 Nov 2025 | 31 Mar 2029 | 20 MW |
| Boyndie Solar | 7 Nov 2025 | 30 Sep 2029 | 69.9 MW |
| YAMAL BESS | 22 Jul 2025 | 31 Oct 2033 | 50 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2023 | 6.9 MW |
| 2027 | 42.1 MW |
| 2028 | 92 MW |
| 2029 | 181.9 MW |
| 2033 | 231.9 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Mount Blairy | 35.2 MW | 0 MW | 31 Oct 2027 | 2 | gate 2 | Scoping |
| 2 | Macduff Battery Storage | 49.9 MW | 35.2 MW | 30 Jun 2028 | 2 | gate 2 | Consents Approved |
| 3 | Brackenhills Wind | 2.3 MW | 85.1 MW | 20 Jul 2023 | not stated | gate not printed | Scoping |
| 4 | Carlincraig Wind | 4.6 MW | 87.4 MW | 30 Sep 2023 | not stated | gate not printed | Consents Approved |
| 5 | Denhead Solar Farm | 20 MW | 92 MW | 31 Mar 2029 | not stated | gate not printed | Scoping |
| 6 | Boyndie Solar | 69.9 MW | 112 MW | 30 Sep 2029 | not stated | gate not printed | Scoping |
| 7 | YAMAL BESS | 50 MW | 181.9 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2023 | 2 | 6.9 MW |
| 2027 | 1 | 35.2 MW |
| 2028 | 1 | 49.9 MW |
| 2029 | 2 | 89.9 MW |
| 2033 | 1 | 50 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Boyndie Solar | Hybrid | 69.9 MW | 30 Sep 2029 | Scoping |
| YAMAL BESS | Battery storage | 50 MW | 31 Oct 2033 | Scoping |
| Macduff Battery Storage | Battery storage | 49.9 MW | 30 Jun 2028 | Consents Approved |
| Mount Blairy | Solar | 35.2 MW | 31 Oct 2027 | Scoping |
| Denhead Solar Farm | Solar | 20 MW | 31 Mar 2029 | Scoping |
| Carlincraig Wind | Onshore wind | 4.6 MW | 30 Sep 2023 | Consents Approved |
| Milton of Fisherie Wind Generating Station | Onshore wind | 4.6 MW | not stated | Built |
| Easter Melrose Wind Generating Station | Onshore wind | 2.7 MW | not stated | Built |
| Gawnsmoss Wind Generating Station | Onshore wind | 2.4 MW | not stated | Built |
| Brackenhills Wind | Onshore wind | 2.3 MW | 20 Jul 2023 | Scoping |