Market Harborough 400kV Substation

NESO connection site, host NGET.

Contracted here1.56 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date31 Jul 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,560 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Braybrooke31 May 202431 Jul 2032600 MW
Market Harborough GEC (Ethos Green)31 May 202431 Oct 2032560 MW
ER MKH Energy31 May 202428 Oct 2033400 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2032: 1.2 GW2033: 1.6 GW203220331.6 GW
0 MW1.0 GW2.0 GW2032: 1.2 GW2033: 1.6 GW203220331.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20321,160 MW
20331,560 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Braybrooke600 MW0 MW31 Jul 20321gate 1Scoping
2Market Harborough GEC (Ethos Green)560 MW600 MW31 Oct 20321gate 1Awaiting Consents
3ER MKH Energy400 MW1,160 MW28 Oct 20331gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203221,160 MW
20331400 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
BraybrookeBattery storage600 MW31 Jul 2032Scoping
Market Harborough GEC (Ethos Green)Hybrid560 MW31 Oct 2032Awaiting Consents
ER MKH EnergyHybrid400 MW28 Oct 2033Scoping

Supported by National Energy SO Open Data