The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Millbrook Power
31 May 2024 to 28 Jun 2024, date already passed (gate not printed) - Marston Farm 2
31 May 2024 to 31 Oct 2032 (gate 1) - Lightsource Marston Vale 240MW PV+BESS
31 May 2024 to 31 Oct 2034 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Millbrook Power | 31 May 2024 | 28 Jun 2024 | 299 MW |
| Marston Farm 2 | 31 May 2024 | 31 Oct 2032 | 350 MW |
| Lightsource Marston Vale 240MW PV+BESS | 31 May 2024 | 31 Oct 2034 | 240 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 299 MW |
| 2032 | 649 MW |
| 2034 | 889 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Millbrook Power | 299 MW | 0 MW | 28 Jun 2024 | not stated | gate not printed | Under Construction/Commissioning |
| 2 | Marston Farm 2 | 350 MW | 299 MW | 31 Oct 2032 | 1 | gate 1 | Scoping |
| 3 | Lightsource Marston Vale 240MW PV+BESS | 240 MW | 649 MW | 31 Oct 2034 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 299 MW |
| 2032 | 1 | 350 MW |
| 2034 | 1 | 240 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Marston Farm 2 | Hybrid | 350 MW | 31 Oct 2032 | Scoping |
| Millbrook Power | Gas | 299 MW | 28 Jun 2024 | Under Construction/Commissioning |
| Lightsource Marston Vale 240MW PV+BESS | Hybrid | 240 MW | 31 Oct 2034 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.