Marston Vale 400kV Substation

NESO connection site, host NGET.

Contracted here0.89 GWNot yet connected, as printed
Entries in the queue3entries with a printed MW
Earliest connection date28 Jun 2024Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue889 MW across the first 3 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Millbrook Power31 May 202428 Jun 2024299 MW
Marston Farm 231 May 202431 Oct 2032350 MW
Lightsource Marston Vale 240MW PV+BESS31 May 202431 Oct 2034240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2024: 299 MW2032: 649 MW2034: 889 MW202420262028203020322034889 MW
0 MW500 MW1.0 GW2024: 299 MW2032: 649 MW2034: 889 MW2024202720302034889 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2024299 MW
2032649 MW
2034889 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Millbrook Power299 MW0 MW28 Jun 2024not statedgate not printedUnder Construction/Commissioning
2Marston Farm 2350 MW299 MW31 Oct 20321gate 1Scoping
3Lightsource Marston Vale 240MW PV+BESS240 MW649 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20241299 MW
20321350 MW
20341240 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Marston Farm 2Hybrid350 MW31 Oct 2032Scoping
Millbrook PowerGas299 MW28 Jun 2024Under Construction/Commissioning
Lightsource Marston Vale 240MW PV+BESSHybrid240 MW31 Oct 2034Scoping