N84 Grid

Melksham 400kV Substation

NESO connection site, host NGET.

Contracted here1.92 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date26 Jun 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue1,922.4 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Melksham (Tertiary)31 May 202426 Jun 202657 MW
JBM Solar 13 - Melksham31 May 202417 Jul 202649.9 MW
Melksham31 May 202431 Jul 2030500 MW
South Brook31 May 202428 Jun 203735.5 MW
Melksham BESS & PV31 May 202415 Oct 2037800 MW
Melkshem (Cartridge Farm)31 May 202431 Oct 2037480 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2026: 107 MW2030: 607 MW2037: 1.9 GW2026202820302032203420371.9 GW
0 MW1.0 GW2.0 GW2026: 107 MW2030: 607 MW2037: 1.9 GW202620292032203520371.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2026106.9 MW
2030606.9 MW
20371,922.4 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Melksham (Tertiary)57 MW0 MW26 Jun 2026not statedgate not printedScoping
2JBM Solar 13 - Melksham49.9 MW57 MW17 Jul 2026not statedgate not printedScoping
3Melksham500 MW106.9 MW31 Jul 2030not statedgate not printedAwaiting Consents
4South Brook35.5 MW606.9 MW28 Jun 2037not statedgate not printedAwaiting Consents
5Melksham BESS & PV800 MW642.4 MW15 Oct 2037not statedgate not printedScoping
6Melkshem (Cartridge Farm)480 MW1,442.4 MW31 Oct 2037not statedgate not printedAwaiting Consents

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20262106.9 MW
20301500 MW
203731,315.5 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Melksham BESS & PVHybrid800 MW15 Oct 2037Scoping
Melksham (LIME DOWN SOLAR PARK LIMITED)Hybrid500 MW31 Jul 2030Awaiting Consents
Melkshem (Cartridge Farm)Battery storage480 MW31 Oct 2037Awaiting Consents
Melksham (Tertiary)Hybrid57 MW26 Jun 2026Scoping
JBM Solar 13 - MelkshamHybrid49.9 MW17 Jul 2026Scoping
South BrookHybrid35.5 MW28 Jun 2037Awaiting Consents
Melksham Grid Park ESS & PVHybrid0 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.