N84 Grid

MID WALES CONNECTION NODE A 400KV SUBSTATION

NESO connection site, host NGET.

Contracted here0.97 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Oct 2037Date printed in the register

The queue, in order

Order calculated by N84
First in queue971 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Mynydd Y Gwynt22 Jul 202530 Oct 2037100 MW
Garn Fach Wind Farm31 May 202431 Oct 2037162 MW
Galileo 0921 Mar 202531 Oct 2037297 MW
Lightsource Berthlwyd20 Dec 202431 Oct 2037240 MW
GALILEO 08 LIMITED22 Jul 202531 Oct 2037100 MW
Calon y Gwynt22 Jul 202531 Oct 203772 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW500 MW1.0 GW2037: 971 MW2037971 MW
0 MW500 MW1.0 GW2037: 971 MW2037971 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2037971 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Mynydd Y Gwynt100 MW0 MW30 Oct 2037not statedgate not printedScoping
2Garn Fach Wind Farm162 MW100 MW31 Oct 2037not statedgate not printedScoping
3Galileo 09297 MW262 MW31 Oct 20371gate 1Scoping
4Lightsource Berthlwyd240 MW559 MW31 Oct 20371gate 1Scoping
5GALILEO 08 LIMITED100 MW799 MW31 Oct 2037not statedgate not printedScoping
6Calon y Gwynt72 MW899 MW31 Oct 2037not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20376971 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Galileo 09Hybrid297 MW31 Oct 2037Scoping
Lightsource BerthlwydHybrid240 MW31 Oct 2037Scoping
Garn Fach Wind FarmHybrid162 MW31 Oct 2037Scoping
Mynydd Y GwyntHybrid100 MW30 Oct 2037Scoping
GALILEO 08 LIMITEDHybrid100 MW31 Oct 2037Scoping
Calon y GwyntHybrid72 MW31 Oct 2037Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.