N84 Grid

Milton of Craigie GSP

NESO connection site, host SHET.

Contracted here0.16 GWNot yet connected, as printed
Entries in the queue6entries with a printed MW
Earliest connection date30 Apr 2026Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue162.95 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Wellbank Solar Farm7 Nov 202531 Dec 202625 MW
Mid Craigie BESS7 Nov 202531 Jul 202749.9 MW
Claverhouse Gas Generation7 Nov 202530 Apr 202619.9 MW
Milton of Craigie GSP7 Nov 202531 Dec 20260.25 MW
Pitkerro Road31 May 202431 Oct 203349.9 MW
Barns of Wedderburn (ABEI ENERGY GREEN VI)22 Jul 202531 Oct 203318 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW100 MW200 MW2026: 45 MW2027: 95 MW2033: 163 MW20262027202820292030203120322033163 MW
0 MW100 MW200 MW2026: 45 MW2027: 95 MW2033: 163 MW2026202820302033163 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
202645.15 MW
202795.05 MW
2033162.95 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Wellbank Solar Farm25 MW0 MW31 Dec 20262gate 2Consents Approved
2Mid Craigie BESS49.9 MW25 MW31 Jul 20272gate 2Awaiting Consents
3Claverhouse Gas Generation19.9 MW74.9 MW30 Apr 2026not statedgate not printedScoping
4Milton of Craigie GSP0.25 MW94.8 MW31 Dec 2026not statedgate not printedScoping
5Pitkerro Road49.9 MW95.05 MW31 Oct 2033not statedgate not printedScoping
6Barns of Wedderburn (ABEI ENERGY GREEN VI)18 MW144.95 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2026345.15 MW
2027149.9 MW
2033267.9 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Mid Craigie BESSBattery storage49.9 MW31 Jul 2027Awaiting Consents
Pitkerro RoadBattery storage49.9 MW31 Oct 2033Scoping
Wellbank Solar FarmSolar25 MW31 Dec 2026Consents Approved
Claverhouse Gas GenerationGas19.9 MW30 Apr 2026Scoping
Barns of Wedderburn (ABEI ENERGY GREEN VI)Hybrid18 MW31 Oct 2033Scoping
Baldovie EfWBiomass and waste10 MWnot statedBuilt
Milton of Craigie GSP (Scottish Hydro Electric Power Distribution Plc)Hybrid0.25 MW31 Dec 2026Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.