The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Tacher Wind
7 Nov 2025 to 31 Aug 2025, date already passed (gate 2) - Golticlay Wind Farm
7 Nov 2025 to 31 Jul 2026, date already passed (gate 2) - Golticlay Wind Farm
7 Nov 2025 to 31 Jul 2026, date already passed (gate 2) - Toftinghall BESS 1
7 Nov 2025 to 30 Sep 2026, date already passed (gate 2) - Tacher Wind
7 Nov 2025 to 31 Aug 2030 (gate 2)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Tacher Wind | 7 Nov 2025 | 31 Aug 2025 | 9.99 MW |
| Golticlay Wind Farm | 7 Nov 2025 | 31 Jul 2026 | 50.07 MW |
| Golticlay Wind Farm | 7 Nov 2025 | 31 Jul 2026 | 7.93 MW |
| Toftinghall BESS 1 | 7 Nov 2025 | 30 Sep 2026 | 25.2 MW |
| Tacher Wind | 7 Nov 2025 | 31 Aug 2030 | 2.91 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2025 | 9.99 MW |
| 2026 | 93.19 MW |
| 2030 | 96.1 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Tacher Wind | 9.99 MW | 0 MW | 31 Aug 2025 | 2 | gate 2 | Scoping |
| 2 | Golticlay Wind Farm | 50.07 MW | 9.99 MW | 31 Jul 2026 | 2 | gate 2 | Awaiting Consents |
| 3 | Golticlay Wind Farm | 7.93 MW | 60.06 MW | 31 Jul 2026 | 2 | gate 2 | Scoping |
| 4 | Toftinghall BESS 1 | 25.2 MW | 67.99 MW | 30 Sep 2026 | 2 | gate 2 | Consents Approved |
| 5 | Tacher Wind | 2.91 MW | 93.19 MW | 31 Aug 2030 | 2 | gate 2 | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2025 | 1 | 9.99 MW |
| 2026 | 3 | 83.2 MW |
| 2030 | 1 | 2.91 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Golticlay Wind Farm | Onshore wind | 58 MW | 31 Jul 2026 | Scoping |
| Causeymire | Onshore wind | 48.3 MW | not stated | Built |
| Toftinghall BESS 1 | Battery storage | 25.2 MW | 30 Sep 2026 | Consents Approved |
| Burn of Whilk Wind Farm | Onshore wind | 22.5 MW | not stated | Built |
| Wathegar 2 Windfarm | Onshore wind | 22.5 MW | not stated | Built |
| Tacher Wind | Onshore wind | 12.9 MW | 31 Aug 2030 | Scoping |