N84 Grid

Mybster 1 132/33kV Substation

NESO connection site, host SHET.

Contracted here0.10 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Aug 2025Already passed, not yet connected

The queue, in order

Order calculated by N84
First in queue96.1 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Tacher Wind7 Nov 202531 Aug 20259.99 MW
Golticlay Wind Farm7 Nov 202531 Jul 202650.07 MW
Golticlay Wind Farm7 Nov 202531 Jul 20267.93 MW
Toftinghall BESS 17 Nov 202530 Sep 202625.2 MW
Tacher Wind7 Nov 202531 Aug 20302.91 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW50 MW100 MW2025: 10 MW2026: 93 MW2030: 96 MW20252026202720282029203096 MW
0 MW50 MW100 MW2025: 10 MW2026: 93 MW2030: 96 MW202520272029203096 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20259.99 MW
202693.19 MW
203096.1 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Tacher Wind9.99 MW0 MW31 Aug 20252gate 2Scoping
2Golticlay Wind Farm50.07 MW9.99 MW31 Jul 20262gate 2Awaiting Consents
3Golticlay Wind Farm7.93 MW60.06 MW31 Jul 20262gate 2Scoping
4Toftinghall BESS 125.2 MW67.99 MW30 Sep 20262gate 2Consents Approved
5Tacher Wind2.91 MW93.19 MW31 Aug 20302gate 2Scoping

Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
202519.99 MW
2026383.2 MW
203012.91 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Golticlay Wind FarmOnshore wind58 MW31 Jul 2026Scoping
CauseymireOnshore wind48.3 MWnot statedBuilt
Toftinghall BESS 1Battery storage25.2 MW30 Sep 2026Consents Approved
Burn of Whilk Wind FarmOnshore wind22.5 MWnot statedBuilt
Wathegar 2 WindfarmOnshore wind22.5 MWnot statedBuilt
Tacher WindOnshore wind12.9 MW31 Aug 2030Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.