Mybster 4 132/33 kV GSP Substation

NESO connection site, host SHET.

Contracted here0.07 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date31 Oct 2034Date printed in the register

The queue, in order

Order calculated by N84
First in queue69.6 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Mybster BESS_Ver27 Nov 202531 Oct 203430 MW
Causeymire 2 Wind Farm21 Mar 202531 Oct 203439.6 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW40 MW80 MW2034: 70 MW203470 MW
0 MW40 MW80 MW2034: 70 MW203470 MW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
203469.6 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Mybster BESS_Ver230 MW0 MW31 Oct 2034not statedgate not printedScoping
2Causeymire 2 Wind Farm39.6 MW30 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026; the NESO Embedded Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
2034269.6 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Causeymire 2 Wind FarmOnshore wind39.6 MW31 Oct 2034Scoping
Mybster BESS_Ver2Battery storage30 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data