N84 Grid

Near Branxton 400kV Substation

NESO connection site, host SPT.

Contracted here2.90 GWNot yet connected, as printed
Entries in the queue2entries with a printed MW
Earliest connection date30 Jun 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue2,900 MW across the first 2 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
INTOG 222 Jul 202530 Jun 20321,400 MW
Phoenix 1B Offshore Wind Farm31 May 202431 Oct 20331,500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW2.0 GW4.0 GW2032: 1.4 GW2033: 2.9 GW203220332.9 GW
0 MW2.0 GW4.0 GW2032: 1.4 GW2033: 2.9 GW203220332.9 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
20321,400 MW
20332,900 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1INTOG 21,400 MW0 MW30 Jun 2032not statedgate not printedScoping
2Phoenix 1B Offshore Wind Farm1,500 MW1,400 MW31 Oct 2033not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
203211,400 MW
203311,500 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Phoenix 1B Offshore Wind FarmOffshore wind1,500 MW31 Oct 2033Scoping
INTOG 2Offshore wind1,400 MW30 Jun 2032Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.