The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Ardonald Wind Farm
27 Sep 2024 to 31 Oct 2033 (gate not printed) - Rattray BESS and Solar Plant
22 Jul 2025 to 31 Oct 2037 (gate 1) - Glenfiddich West
22 Jul 2025 to 31 Oct 2037 (gate 1) - Longhaven Energy Storage Centre
22 Jul 2025 to 31 Oct 2037 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Ardonald Wind Farm | 27 Sep 2024 | 31 Oct 2033 | 200 MW |
| Rattray BESS and Solar Plant | 22 Jul 2025 | 31 Oct 2037 | 300 MW |
| Glenfiddich West | 22 Jul 2025 | 31 Oct 2037 | 600 MW |
| Longhaven Energy Storage Centre | 22 Jul 2025 | 31 Oct 2037 | 500 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2033 | 200 MW |
| 2037 | 1,600 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Ardonald Wind Farm | 200 MW | 0 MW | 31 Oct 2033 | not stated | gate not printed | Scoping |
| 2 | Rattray BESS and Solar Plant | 300 MW | 200 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 3 | Glenfiddich West | 600 MW | 500 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
| 4 | Longhaven Energy Storage Centre | 500 MW | 1,100 MW | 31 Oct 2037 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2033 | 1 | 200 MW |
| 2037 | 3 | 1,400 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Glenfiddich West | Hybrid | 600 MW | 31 Oct 2037 | Scoping |
| Longhaven Energy Storage Centre | Hybrid | 500 MW | 31 Oct 2037 | Scoping |
| Rattray BESS and Solar Plant | Hybrid | 300 MW | 31 Oct 2037 | Scoping |
| Ardonald Wind Farm | Hybrid | 200 MW | 31 Oct 2033 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.