The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Fernishaw Farm PV
7 Nov 2025 to 30 Oct 2026 (gate 2) - Brownhill Farm Windfarm
7 Nov 2025 to 31 Dec 2024, date already passed (gate not printed) - Hartwood Wind Farm
7 Nov 2025 to 31 Mar 2026, date already passed (gate not printed) - Dewshill Windfarm
7 Nov 2025 to 30 Apr 2026, date already passed (gate not printed) - Greenside Farm PP
7 Nov 2025 to 30 Jun 2026, date already passed (gate not printed) - Newarthill GSP
7 Nov 2025 to 28 Apr 2028 (gate not printed) - Newarthill GSP
7 Nov 2025 to 31 Oct 2034 (gate not printed) - Motherwell 400MW BESS (Formerly Castlehill BESS)
31 May 2024 to 30 Apr 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Fernishaw Farm PV | 7 Nov 2025 | 30 Oct 2026 | 49.9 MW |
| Brownhill Farm Windfarm | 7 Nov 2025 | 31 Dec 2024 | 8.48 MW |
| Hartwood Wind Farm | 7 Nov 2025 | 31 Mar 2026 | 18.7 MW |
| Dewshill Windfarm | 7 Nov 2025 | 30 Apr 2026 | 10.6 MW |
| Greenside Farm PP | 7 Nov 2025 | 30 Jun 2026 | 28.8 MW |
| Newarthill GSP | 7 Nov 2025 | 28 Apr 2028 | 20 MW |
| Newarthill GSP | 7 Nov 2025 | 31 Oct 2034 | 29.9 MW |
| Motherwell 400MW BESS (Formerly Castlehill BESS) | 31 May 2024 | 30 Apr 2035 | 400 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2024 | 8.48 MW |
| 2026 | 116.48 MW |
| 2028 | 136.48 MW |
| 2034 | 166.38 MW |
| 2035 | 566.38 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Fernishaw Farm PV | 49.9 MW | 0 MW | 30 Oct 2026 | 2 | gate 2 | Consents Approved |
| 2 | Brownhill Farm Windfarm | 8.48 MW | 49.9 MW | 31 Dec 2024 | not stated | gate not printed | Scoping |
| 3 | Hartwood Wind Farm | 18.7 MW | 58.38 MW | 31 Mar 2026 | not stated | gate not printed | Awaiting Consents |
| 4 | Dewshill Windfarm | 10.6 MW | 77.08 MW | 30 Apr 2026 | not stated | gate not printed | Scoping |
| 5 | Greenside Farm PP | 28.8 MW | 87.68 MW | 30 Jun 2026 | not stated | gate not printed | Scoping |
| 6 | Newarthill GSP | 20 MW | 116.48 MW | 28 Apr 2028 | not stated | gate not printed | Scoping |
| 7 | Newarthill GSP | 29.9 MW | 136.48 MW | 31 Oct 2034 | not stated | gate not printed | Scoping |
| 8 | Motherwell 400MW BESS (Formerly Castlehill BESS) | 400 MW | 166.38 MW | 30 Apr 2035 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO Embedded Register, file dated 20 Oct 2026; the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2024 | 1 | 8.48 MW |
| 2026 | 4 | 108 MW |
| 2028 | 1 | 20 MW |
| 2034 | 1 | 29.9 MW |
| 2035 | 1 | 400 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Motherwell 400MW BESS (Formerly Castlehill BESS) | Battery storage | 400 MW | 30 Apr 2035 | Scoping |
| Fernishaw Farm PV | Solar | 49.9 MW | 30 Oct 2026 | Consents Approved |
| Newarthill GSP (SP DISTRIBUTION PLC) | Battery storage | 49.9 MW | 31 Oct 2034 | Scoping |
| Greenside Farm PP | Battery storage | 28.8 MW | 30 Jun 2026 | Scoping |
| Hartwood Wind Farm | Onshore wind | 18.7 MW | 31 Mar 2026 | Awaiting Consents |
| Levenseat Quarry | Onshore wind | 11 MW | not stated | Built |
| Dewshill Windfarm | Onshore wind | 10.6 MW | 30 Apr 2026 | Scoping |
| Brownhill Farm Windfarm | Onshore wind | 8.48 MW | 31 Dec 2024 | Scoping |