N84 Grid

North Anglia Connection Node E 400kV Substation

NESO connection site, host NGET.

Contracted here2.39 GWNot yet connected, as printed
Entries in the queue7entries with a printed MW
Earliest connection date31 Oct 2032Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,890 MW across the first 6 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
EPL Suffolk31 May 202431 Oct 2032480 MW
Yaxley31 May 202431 Oct 2034520 MW
Noventum Yaxley31 May 202431 Oct 2034150 MW
Lightsource Yaxley PV31 May 202431 Oct 2034240 MW
Yaxley BESS31 May 202431 Oct 2034200 MW
Zenobe Yaxley BESS27 Sep 202431 Oct 2034300 MW
Dove Solar31 May 202431 Oct 2034500 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.3 GW2.5 GW2032: 480 MW2034: 2.4 GW2032203320342.4 GW
0 MW1.3 GW2.5 GW2032: 480 MW2034: 2.4 GW2032203320342.4 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2032480 MW
20342,390 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1EPL Suffolk480 MW0 MW31 Oct 20321gate 1Scoping
2Yaxley520 MW480 MW31 Oct 2034not statedgate not printedAwaiting Consents
3Noventum Yaxley150 MW1,000 MW31 Oct 20341gate 1Scoping
4Lightsource Yaxley PV240 MW1,150 MW31 Oct 20341gate 1Scoping
5Yaxley BESS200 MW1,390 MW31 Oct 2034not statedgate not printedScoping
6Zenobe Yaxley BESS300 MW1,590 MW31 Oct 2034not statedgate not printedScoping
7Dove Solar500 MW1,890 MW31 Oct 20341gate 1Scoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20321480 MW
203461,910 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
YaxleyHybrid520 MW31 Oct 2034Awaiting Consents
Dove SolarHybrid500 MW31 Oct 2034Scoping
EPL SuffolkHybrid480 MW31 Oct 2032Scoping
Zenobe Yaxley BESSBattery storage300 MW31 Oct 2034Scoping
Lightsource Yaxley PVHybrid240 MW31 Oct 2034Scoping
Yaxley BESSBattery storage200 MW31 Oct 2034Scoping
Noventum YaxleyHybrid150 MW31 Oct 2034Scoping

Supported by National Energy SO Open Data

Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.