The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- GF Thornton Energy BESS
31 May 2024 to 30 Oct 2035 (gate 1) - Chapel Rush Solar
27 Sep 2024 to 30 Oct 2035 (gate 1)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| GF Thornton Energy BESS | 31 May 2024 | 30 Oct 2035 | 400 MW |
| Chapel Rush Solar | 27 Sep 2024 | 30 Oct 2035 | 600 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2035 | 1,000 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | GF Thornton Energy BESS | 400 MW | 0 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 2 | Chapel Rush Solar | 600 MW | 400 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2035 | 2 | 1,000 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Chapel Rush Solar | Hybrid | 600 MW | 30 Oct 2035 | Scoping |
| GF Thornton Energy BESS | Battery storage | 400 MW | 30 Oct 2035 | Scoping |
Supported by National Energy SO Open Data
Data as published by the named source on the stated date. N84 may contain matching or processing errors. Not investment, legal or technical advice. The official register prevails.