The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Norton PV and BESS
31 May 2024 to 31 Oct 2027 (gate 2) - Norton
31 May 2024 to 1 Jun 2029 (gate not printed) - Al Boum Photo (Norton)
31 May 2024 to 31 Oct 2031 (gate not printed) - Norton Solar Farm
31 May 2024 to 31 Oct 2031 (gate not printed) - Hill House Farm Solar and Storage
21 Mar 2025 to 30 Oct 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Norton PV and BESS | 31 May 2024 | 31 Oct 2027 | 40.9 MW |
| Norton | 31 May 2024 | 1 Jun 2029 | 57 MW |
| Al Boum Photo (Norton) | 31 May 2024 | 31 Oct 2031 | 275 MW |
| Norton Solar Farm | 31 May 2024 | 31 Oct 2031 | 180 MW |
| Hill House Farm Solar and Storage | 21 Mar 2025 | 30 Oct 2035 | 99.9 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2027 | 40.9 MW |
| 2029 | 97.9 MW |
| 2031 | 552.9 MW |
| 2035 | 652.8 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Norton PV and BESS | 40.9 MW | 0 MW | 31 Oct 2027 | 2 | gate 2 | Consents Approved |
| 2 | Norton | 57 MW | 40.9 MW | 1 Jun 2029 | not stated | gate not printed | Awaiting Consents |
| 3 | Al Boum Photo (Norton) | 275 MW | 97.9 MW | 31 Oct 2031 | not stated | gate not printed | Consents Approved |
| 4 | Norton Solar Farm | 180 MW | 372.9 MW | 31 Oct 2031 | not stated | gate not printed | Scoping |
| 5 | Hill House Farm Solar and Storage | 99.9 MW | 552.9 MW | 30 Oct 2035 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2027 | 1 | 40.9 MW |
| 2029 | 1 | 57 MW |
| 2031 | 2 | 455 MW |
| 2035 | 1 | 99.9 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Al Boum Photo (Norton) | Battery storage | 275 MW | 31 Oct 2031 | Consents Approved |
| Norton Solar Farm | Solar | 180 MW | 31 Oct 2031 | Scoping |
| Hill House Farm Solar and Storage | Hybrid | 99.9 MW | 30 Oct 2035 | Scoping |
| Norton (BAYWA R.E. UK LIMITED) | Battery storage | 57 MW | 1 Jun 2029 | Awaiting Consents |
| Norton PV and BESS | Hybrid | 40.9 MW | 31 Oct 2027 | Consents Approved |
| Norton GSP (NORTHERN POWERGRID (NORTHEAST) PLC) | Hybrid | 0 MW | not stated | Scoping |