Norton East 400kV Substation

NESO connection site, host NGET.

Contracted here1.63 GWNot yet connected, as printed
Entries in the queue5entries with a printed MW
Earliest connection date31 Oct 2031Date printed in the register

The queue, in order

Order calculated by N84
First in queue1,630 MW across the first 5 projects
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Dates in the queue

From the earliest date we hold to the connection date printed, in queue order

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. Start is the accepted date as printed, else the date N84 first saw the row.
Table view
Dates in the queue
ProjectFromConnection dateMW
Zenobe Norton31 May 202431 Oct 2031150 MW
Norton31 May 202431 Oct 2032400 MW
Letch Beck Energy Park31 May 202431 Oct 2033600 MW
Lightsource Norton East PV31 May 202430 Oct 2035240 MW
Grindon Grange31 May 202430 Oct 2035240 MW

Contracted MW as dates arrive

Running total by connection year, years to scale

0 MW1.0 GW2.0 GW2031: 150 MW2032: 550 MW2033: 1.2 GW2035: 1.6 GW203120322033203420351.6 GW
0 MW1.0 GW2.0 GW2031: 150 MW2032: 550 MW2033: 1.2 GW2035: 1.6 GW2031203320351.6 GW
Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.
Table view
Cumulative MW by connection year
YearCumulative MW
2031150 MW
2032550 MW
20331,150 MW
20351,630 MW

MW ahead in N84's order: calculator

Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator.

Queue

Queue (calculated by N84, method n84_order_v2)
Placecalculated by N84ProjectMW (as published)MW ahead (N84 order)Connection dateGateOrder groupStatus (as printed)
1Zenobe Norton150 MW0 MW31 Oct 20311gate 1Awaiting Consents
2Norton400 MW150 MW31 Oct 20321gate 1Scoping
3Letch Beck Energy Park600 MW550 MW31 Oct 20331gate 1Scoping
4Lightsource Norton East PV240 MW1,150 MW30 Oct 20351gate 1Scoping
5Grindon Grange240 MW1,390 MW30 Oct 2035not statedgate not printedScoping

Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order

Contracted MW by effective-from year, as published
Year (MW effective from)ProjectsMW
20311150 MW
20321400 MW
20331600 MW
20352480 MW

Projects recorded at this site

Projects recorded at this site, as printed
Project (as published)TechnologyMWConnection dateStatus (as printed)
Letch Beck Energy ParkHybrid600 MW31 Oct 2033Scoping
NortonHybrid400 MW31 Oct 2032Scoping
Grindon GrangeHybrid240 MW30 Oct 2035Scoping
Lightsource Norton East PVHybrid240 MW30 Oct 2035Scoping
Zenobe NortonBattery storage150 MW31 Oct 2031Awaiting Consents