The queue, in order
Dates in the queue
From the earliest date we hold to the connection date printed, in queue order
- Zenobe Norton
31 May 2024 to 31 Oct 2031 (gate 1) - Norton
31 May 2024 to 31 Oct 2032 (gate 1) - Letch Beck Energy Park
31 May 2024 to 31 Oct 2033 (gate 1) - Lightsource Norton East PV
31 May 2024 to 30 Oct 2035 (gate 1) - Grindon Grange
31 May 2024 to 30 Oct 2035 (gate not printed)
Table view
| Project | From | Connection date | MW |
|---|---|---|---|
| Zenobe Norton | 31 May 2024 | 31 Oct 2031 | 150 MW |
| Norton | 31 May 2024 | 31 Oct 2032 | 400 MW |
| Letch Beck Energy Park | 31 May 2024 | 31 Oct 2033 | 600 MW |
| Lightsource Norton East PV | 31 May 2024 | 30 Oct 2035 | 240 MW |
| Grindon Grange | 31 May 2024 | 30 Oct 2035 | 240 MW |
Contracted MW as dates arrive
Running total by connection year, years to scale
Table view
| Year | Cumulative MW |
|---|---|
| 2031 | 150 MW |
| 2032 | 550 MW |
| 2033 | 1,150 MW |
| 2035 | 1,630 MW |
Queue
| Placecalculated by N84 | Project | MW (as published) | MW ahead (N84 order) | Connection date | Gate | Order group | Status (as printed) |
|---|---|---|---|---|---|---|---|
| 1 | Zenobe Norton | 150 MW | 0 MW | 31 Oct 2031 | 1 | gate 1 | Awaiting Consents |
| 2 | Norton | 400 MW | 150 MW | 31 Oct 2032 | 1 | gate 1 | Scoping |
| 3 | Letch Beck Energy Park | 600 MW | 550 MW | 31 Oct 2033 | 1 | gate 1 | Scoping |
| 4 | Lightsource Norton East PV | 240 MW | 1,150 MW | 30 Oct 2035 | 1 | gate 1 | Scoping |
| 5 | Grindon Grange | 240 MW | 1,390 MW | 30 Oct 2035 | not stated | gate not printed | Scoping |
Receipt: MW and dates as printed in the NESO TEC Register, file dated 20 Oct 2026. Order calculated by N84: printed queue position where the register gives one; otherwise entries printed as Gate 2 first, then every other entry by connection date. The register prints no gate for many contracted entries; N84 does not guess their position. Not published by the operator. How we order
| Year (MW effective from) | Projects | MW |
|---|---|---|
| 2031 | 1 | 150 MW |
| 2032 | 1 | 400 MW |
| 2033 | 1 | 600 MW |
| 2035 | 2 | 480 MW |
Projects recorded at this site
| Project (as published) | Technology | MW | Connection date | Status (as printed) |
|---|---|---|---|---|
| Letch Beck Energy Park | Hybrid | 600 MW | 31 Oct 2033 | Scoping |
| Norton | Hybrid | 400 MW | 31 Oct 2032 | Scoping |
| Grindon Grange | Hybrid | 240 MW | 30 Oct 2035 | Scoping |
| Lightsource Norton East PV | Hybrid | 240 MW | 30 Oct 2035 | Scoping |
| Zenobe Norton | Battery storage | 150 MW | 31 Oct 2031 | Awaiting Consents |
Supported by National Energy SO Open Data